Page 21 - Issue 22
P. 21

Associations                    21


 Engineering  Associations  Botswana  Disputes Under




 Real Estate Institute Of
 Botswana
 TEL: 316 4713
 CELL:72 107 842

 Royal Institution Of Chartered             FIDIC 2017
  Surveyors Botswana Group
 TEL: 310 5494
 CELL: 72 111 201

 Setlogelwa Tsatsing Civil &
 Contractors Association
 CELL: 71 380 505  Introduction               Engineer’s  Determination:  Sub-Clause  agreed or determined, the matter shall
                                              3.7                                be deemed to be a Dispute which may
 Quantity Surveyors Registration   •   The   new   contracts   are               be referred by either party to the DAAB
 Council      approximately 50% longer        1. The Engineer shall consult with both  for  its  decision  under  Sub-Clause  21.4
 Tel: 3956170  •   Much   more   administratively  parties  to  encourage  discussion  and  without a need for a NOD.
              burdensome    with    deeming  endeavouring to reach an agreement.
 For any Ommitted Associations   •   provisions and time bars.  2.  If  agreement  is  reached  the  parties  Sub-Clause 20.1
                                                                                 “A Claim may arise:
              The old clause 20 has been split into  shall sign a Notice to that effect.
 or Corrections to the above   clause 20 and 21 to separate claims  3. If no agreement is reached or the time  (a)  if  the  Employer  considers  that  the
 Information /interivews   and disputes.      limit  under  Sub-Clause  3.7.3  expires  Employer  is  entitled  to  any  additional
 email :  •   More complex approach to drafting.  then  the  Engineer  must  give  a  Notice  payment  from  the  Contractor  (or
          •
              Additional  project  management  and  proceed  immediately  to  make  a  reduction in the Contract Price) and/or
 marketing@engineermagazine.co.bw  tools have been added  decision.              to an extension of the DNP;
                                              4.The  Engineer  shall  make  a  fair  (b) if the Contractor considers that the
          Aims of the Contract                determination of the matter and give a  Contractor is entitled to any additional
                                              Notice of his/her determination.   payments from the Employer and/or to
          •   Clarity, transparency and certainty  5. If a typographical error is discovered  EOT; or if either party considers that he/
          •   Balance and reciprocity         then  either  party  may  request  the  she is entitled to another entitlement or
          •   Project  and  contract  management  Engineer to fix it. The Engineer may also  relief against the other party…”
              techniques                      fix it on his/her own accord.
          •   Dispute avoidance               6.If  either  party  is  unhappy  with  the  What is a “fully detailed claim”? Sub-
                                              determination, it may give a Notice of  clause 20.2.4:
          Aims of the new contracts           Dissatisfaction (NOD).
                                              7.If a NOD is issued the DAAB procedure  1.A detailed description of the event or
            “The core aim of the majority of the  shall apply                    circumstance giving rise to the Claim;
          changes in FIDIC’s 2017 contract updates  8.If no NOD is issued within 28 days of  2.A statement of the contractual and/or
          is  increased  clarity  and  certainty,  the  determination  then  both  parties  other legal basis of the Claim;
          to  reduce  the  risk  of  disagreements  shall  be  taken  to  have  accepted  the  3.All  contemporary  records  on  which
          regarding the interpretation of contract  determination and it shall be treated as  the claiming Party relies; and
          terms  and,  as  a  result,  increase  the  final and binding.         4. Detailed supporting particulars of the
          probability of successful projects.  9.If either party fails to comply with the  amount of additional payment claimed
          Consistent  with  the  above,  FIDIC  has  determination, then the other side may  and/or EOT claimed or extension of the
          improved  the  contract  provisions  refer the dispute to arbitration.   DNP claimed.
          by  making  them  more  prescriptive
          and  introducing  step-by-step  project  What happens if the Engineer does not  Should a time limit be extended? Sub-
          management      and     procedural  give a decision in the required 42 days?  clause 20.2.5:
          mechanisms,  by  setting  out  exactly
          what is expected from the Employer, the  1.   In  the  case  of  a  Claim,  the  •   Whether  or  to  what  extent  the
          Contractor and the Engineer during the  Engineer shall be deemed to have given   other party would be prejudiced by
          performance of the Contract.”       a determination rejecting the Claim; or  acceptance of the late submission;
                                              2.     In  the  case  of  a  matter  to  be  •   In the case of the time


 Issue 22   - Jun/Jul 2019  www.engineermagazine.co.bw  www.engineermagazine.co.bw             Issue 22   - Jun/Jul 2019
   16   17   18   19   20   21   22   23   24   25   26